SAFER is implemented through five interlinked Work Packages (WPs). Each WP has a clear lead partner and a set of tasks, deliverables, and milestones that guide implementation from start to finish.

Project timing reference:

  • M1 = October 2025
  • M36 = September 2028

WP1 — Project Management, Monitoring and Evaluation

Lead: International Hellenic University (IHU) — Greece
Duration: M1–M36 (October 2025 – September 2028)

What WP1 covers

WP1 ensures strong project governance, coordination, reporting, monitoring, quality assurance, and risk management across the whole consortium.

WP1 Tasks

  • T1.1 Project Management
  • T1.2 Financial Issues
  • T1.3 Monitoring and Evaluation

WP1 Deliverables

  • D1.1 — TPM1 - Transnational project meeting n. 1 — Due M2 (November 2025)
  • D1.2 — TPM2-Transnational project meeting n. 2 — Due M14 (November 2026)
  • D1.4 — Progress Report — Due M18 (March 2027)
  • D1.3 — TPM3-Transnational Project Meeting n 3 — Due M26 (November 2027)

WP1 Milestones

  • Milestone 1 — Project Management Plan (PMP) — Due M6 (March 2026)
  • Milestone 2 — Quality and Evaluation Plan (QEP), Intermediate Progress Evaluation Reports — Due M6 (March 2026)
  • Milestone 29 — Consortium Agreement — Due M6 (March 2026)

WP2 — Needs Assessment, Strategic Planning, and Capacity Building

Lead: Uzhhorod National University (UzhNU) — Ukraine
Duration: M1–M12 (October 2025 – September 2026)

What WP2 covers

WP2 identifies partner needs and establishes the strategic and capacity-building foundation for the curricula and digital learning activities that follow.

WP2 Tasks

  • T2.1 Assessment of the needs of higher education institutions (HEIs) for research and teaching on climate change resilience and sustainable agriculture in developing countries.
  • T2.2 Organize institutional workshops to discuss HEIs' needs assessment in the areas of research and teaching on climate change resilience and sustainable agriculture in developing nations.
  • T2.3 Development of a strategic plan
  • T2.4 Organize seminars and workshops to debate and present the strategic plan
  • T2.5 Conducted teacher and staff development training sessions

WP2 Deliverables

  • D2.1 — Analytical report, survey assessment technique and instruments (quantitative research questionnaire and detailed interview guide, sample, etc.) — Due M3 (December 2025)
  • D2.2 — Project implementation plan — Due M6 (March 2026)
  • D2.3 — Project strategic plan — Due M9 (June 2026)
  • D2.4 — Activities program — Due M9 (June 2026)
  • D2.5 — Customized workshops and seminars — Due M12 (September 2026)

WP2 Milestones

  • Milestone 3 — Conducted interviews and a survey — Due M4 (January 2026)
  • Milestone 4 — Analysis of study findings — Due M6 (March 2026)
  • Milestone 5 — Workshop for findings evaluation — Due M6 (March 2026)
  • Milestone 6 — Program working materials on possible development — Due M9 (June 2026)
  • Milestone 7 — Development program's working materials — Due M10 (July 2026)
  • Milestone 8 — Teacher and staff development training sessions — Due M11 (August 2026)
  • Milestone 9 — Updated capacity development program working materials — Due M12 (September 2026)

WP3 — Curriculum Development and Digital Learning

Lead: Varna University of Management (VUM) — Bulgaria
Duration: M6–M30 (March 2026 – March 2028)

What WP3 covers

WP3 develops and pilots the curriculum and learning materials, and establishes the online environment supporting the project’s training and education goals.

WP3 Tasks

  • T3.1 Creating standard operating procedures and templates
  • T3.2 Creating the "Sustainable Agriculture and Food Systems" curriculum
  • T3.3 Creating Materials for Teaching and Training
  • T3.4 Creating an Online Learning Environment
  • T3.5 Training for instructors to deliver the new courses (Training of trainers)
  • T3.6 Pilot testing of the newly developed courses

WP3 Deliverables

  • D3.1 — Techniques and templates (for the training materials and curriculum) — Due M9 (June 2026)
  • D3.3 — Platform for Digital Learning — Due M18 (March 2027)
  • D3.2 — Courses in the existing degree — Due M24 (September 2027)
  • D3.4 — Training workshop for academic Staff — Due M24 (September 2027)
  • D3.5 — Pilot testing in 3 nations — Due M30 (March 2028)

WP3 Milestones

  • Milestone 10 — Establishment of an international research working group — Due M7 (April 2026)
  • Milestone 11 — Techniques and templates (for training materials, digital platforms, and curriculum content) were accepted and used — Due M9 (June 2026)
  • Milestone 28 — Purchase of equipment — Due M10 (July 2026)
  • Milestone 12 — Course outlines created and approved. — Due M16 (January 2027)
  • Milestone 14 — The digital platform was tested and made available — Due M20 (May 2027)
  • Milestone 13 — A collection of English-language teaching and training resources created and approved — Due M24 (September 2027)
  • Milestone 15 — Translation of teaching and training materials is completed. — Due M26 (November 2027)
  • Milestone 16 — Every course topic is available on the digital platform — Due M26 (November 2027)
  • Milestone 17 — Three countries will have scheduled pilot training sessions — Due M28 (January 2028)

WP4 — Community Engagement and Industry Collaboration

Lead: Al-Balqa Applied University (BAU) — Jordan
Duration: M12–M36 (September 2026 – September 2028)

What WP4 covers

WP4 connects the project with communities and industry, supporting local workshops, collaboration mechanisms, and practical links to stakeholders.

WP4 Tasks

  • T4.1 Creation of a Plan for Industry Collaboration and Community Engagement
  • T4.2 Planning (and taking part in) workshops with nearby communities and industries
  • T4.3 Creating the SAFER Network, a collaborative network in the field of sustainable food systems
  • T4.4 Developing relationships with the local businesses

WP4 Deliverables

  • D4.1 — Industry Collaboration and Community Involvement Plan — Due M12 (September 2026)
  • D4.2 — 1st Local workshop of community engagement — Due M14 (November 2026)
  • D4.5 — SAFER Network — Due M18 (March 2027)
  • D4.3 — 2nd Local workshop of community engagement — Due M20 (May 2027)
  • D4.6 — Developed relationships with both governmental and private sector groups — Due M24 (September 2027)
  • D4.4 — 3rd Local workshop of community engagement — Due M26 (November 2027)

WP4 Milestones

  • Milestone 18 — Strategy for Industry Collaboration and Community Involvement — Due M14 (November 2026)
  • Milestone 20 — Establishing SAFER Project network — Due M18 (March 2027)
  • Milestone 21 — Contracts of understanding(MoUs) and agreements for collaboration — Due M24 (September 2027)
  • Milestone 19 — Workshops involving nearby communities and industries — Due M36 (September 2028)

WP5 — Dissemination, Inclusivity, and Sustainability

Lead: Arab Academy for Science, Technology and Maritime Transport (AASTMT) — Egypt
Duration: M1–M36 (October 2025 – September 2028)

What WP5 covers

WP5 ensures visibility, communication, inclusive participation, stakeholder engagement, and long-term sustainability of SAFER results across all partner countries.

WP5 Tasks

  • T5.1 Creation of an Inclusivity and Dissemination Plan
  • T5.2 Primary marketing materials include things like papers and internet advertising materials.
  • T5.3 Interaction with Communities and Stakeholders
  • T5.4 Activities with an Inclusivity Focus
  • T5.5 Workshops & Seminars on Sustainability
  • T5.6 Final Conference and Event on Sustainability

WP5 Deliverables

  • D5.1 — All-inclusive Distribution and Inclusion Strategy — Due M10 (July 2026)
  • D5.2 — Marketing and Outreach Resources — Due M12 (September 2026)
  • D5.4 — Inclusivity-Centered Workshop Resources — Due M15 (December 2026)
  • D5.3 — Report on Activities for Stakeholder Engagement — Due M30 (March 2028)
  • D5.5 — Report on Sustainability Workshop — Due M32 (May 2028)
  • D5.6 — Report from the Final Conference and Sustainability Plan — Due M36 (September 2028)

WP5 Milestones

  • Milestone 22 — Finalized Plan for Dissemination and Inclusivity — Due M6 (March 2026)
  • Milestone 23 — Design of Outreach Materials — Due M12 (September 2026)
  • Milestone 24 — Events for Stakeholder Engagement — Due M18 (March 2027)
  • Milestone 25 — Activities for Inclusivity Placed in Action — Due M24 (September 2027)
  • Milestone 26 — Workshops on sustainability — Due M30 (March 2028)
  • Milestone 27 — Final Meeting and Ceremony — Due M36 (September 2028)